If you’re trying to make a WBS from your suite of 2007 applications, Microsoft Download Center has a Visio add-on that might save you some time.

To get a WBS pumped out quickly, just do the following:

  1. Download and install Microsoft Office Visio 2007 WBS Modeler.
  2. Open Visio, and start from the new WBS Modeler.
  3. Open Project and open the project you want to make a WBS for.
  4. In Visio, click WBS Modeler, then Import From Microsoft Office Project…

Click through a couple more settings and here you have it. An easy WBS, and best of all it is free! When I was looking around the best alternative looks like it will run you around $200.

 

Technorati Tags: ,,
Posted on Sunday, January 11, 2009 12:05 PM Microsoft , How-To | Back to top


Comments on this post: Hot-To: Model a Work Breakdown Structure with Project 2007 and Visio 2007

# re: Hot-To: Model a Work Breakdown Structure with Project 2007 and Visio 2007
Requesting Gravatar...
I have tried to download the wbs modeler from the MS website but unable to. Does anyone have the file, and can they send it to me.
Left by F Ahmed on Feb 20, 2009 6:29 AM

# re: Hot-To: Model a Work Breakdown Structure with Project 2007 and Visio 2007
Requesting Gravatar...
For WBS (work breakdown structure) diagram integrated in MS Project see http://www.wbs-tool.net/wbs/Beispiele/WBStoolMPP.png at http://www.wbs-tool.net
Left by dietmar on Nov 15, 2009 9:33 AM

# re: Hot-To: Model a Work Breakdown Structure with Project 2007 and Visio 2007
Requesting Gravatar...
The Visio 2007 WBS modeler only works with Visio 2007 PROFESSIONAL. Older versions of Visio had an export to Visio feature, but this has been removed and replaced with the Visio 2007 Professional only WBS modeler add-in.
Left by Jerry B on Apr 02, 2010 9:39 AM

# re: Hot-To: Model a Work Breakdown Structure with Project 2007 and Visio 2007
Requesting Gravatar...
jajjajajaja si son dundos ustedes.. ponene cosas q ni saben aqui..
Left by robert on May 03, 2010 5:37 PM

# re: Hot-To: Model a Work Breakdown Structure with Project 2007 and Visio 2007
Requesting Gravatar...
This Add-in works only for Visio 2007 Professional
Left by captain hellfish on Jan 04, 2011 6:46 AM

# re: Hot-To: Model a Work Breakdown Structure with Project 2007 and Visio 2007
Requesting Gravatar...
Does anyone know how to get the total task cost to display in the WBS that is produced in Visio by this method?

Thanks,
Benson
Left by Benson Wallace on Nov 28, 2011 12:23 AM